Fairfield Knockdown Rebuild
A full knockdown rebuild replacing a 1960s fibro home with a modern 4-bedroom, 2-bathroom residence on an R2 lot.
Challenge
The original home contained asbestos cladding requiring licensed removal. The narrow 15m frontage limited vehicle access during demolition. Neighbour setback constraints required careful design coordination with council.
Solution
We managed the asbestos removal through a licensed subcontractor with full WorkCover compliance. The demolition was staged over 2 weeks to minimise disruption. The new home was designed to maximise the 280sqm footprint with a single-storey layout optimised for the block shape.
Result
Completed on time and within the fixed-price contract. The owners moved from a 3-bedroom fibro home into a modern 4-bedroom residence with double garage, open-plan living, and landscaped front and rear yards.