House Demolition and Knockdown Rebuild in Five Dock
Demolition is the quickest part of a Five Dock rebuild. It's also the part that has to be approved first.
If you're searching for house demolition in Five Dock, you probably want the old house gone so a new one can go up. The order matters: approval for the new home, a hazardous materials survey, licensed asbestos removal, disconnections, and only then the machines. Do it the other way round and you're paying holding costs on an empty block.
Short answer
How does house demolition work in Five Dock?
Demolition is normally approved with the new home, in the same complying development certificate or development application to the City of Canada Bay. Before the house comes down, a hazardous materials survey finds any asbestos, a licensed removalist takes it out, and the services are disconnected. Then the house is demolished, the site is cleared and the new build starts.
Written and reviewed by Oliver Alameri
Licensed builder, NSW Contractor Licence 487805C · Founder, Buildana
Fact-checked
Approval comes before the excavator
Demolition is usually part of the approval for the new home rather than a job you do first. Where the new home meets the Housing Code, a private certifier can approve both as complying development, and a CDC must be decided within 20 days where neighbours are notified (10 days otherwise). Otherwise it's a development application to the City of Canada Bay, and a DA has a 40-day assessment period.
Check the planning certificate before you plan on a rebuild at all. If the house is a heritage item or sits in a heritage conservation area, council looks at whether losing it is justified, and complying development is generally not available.
Approve the new house before you knock down the old one.
Asbestos and other hazards
Older houses can hide asbestos in fibro sheeting, eaves, vinyl floors, roofing and pipe lagging. A hazardous materials survey before demolition finds it, along with things like lead paint. Asbestos is then removed by a licensed removalist under SafeWork NSW rules, and the area is cleared before the rest of the house comes down.
Nobody can tell you what's in the walls from the street. That's why the survey comes before any demolition price is treated as firm.
- Hazardous materials survey of the whole house
- Licensed asbestos removal before demolition
- Clearance before demolition continues
Want the old house gone the right way?
Send the Five Dock address and a few photos of the house. Oliver will respond within 4 working hours for a free initial conversation.
0476 300 300Disconnections, neighbours and the street
Electricity, gas, water and sewer are disconnected or capped before the house comes down, and Sydney Water has its own requirements when you build. Phone and internet lines get removed too.
On a suburban street the neighbours live with the job. A dilapidation report on the houses either side records their condition before work starts, which protects everyone if a crack is noticed later. A note to the street before demolition, a tidy site and trucks timed around school runs go a long way.

Site costs: what drives them and who confirms them
Demolition and site costs aren't guessed. Each one has a cause, and someone qualified confirms it before the contract is signed.
- Asbestos removal: the survey sets the scope, the licensed removalist prices it
- Demolition: the size and construction of the house and the access, priced by the demolition contractor after inspection
- Disconnections: set by each service provider
- Footings and slab: set by the geotechnical report and the engineer
- Levels and boundaries: confirmed by the surveyor
- Contributions: set by the City of Canada Bay's contributions plan, confirmed by council or the certifier
The new home
For the new home, our knockdown rebuild benchmark from Rawlinsons' Sydney rates is single storey $565k–$980k + GST, double storey $735k–$1.27M + GST. That's the build only, before demolition and the site costs above.
For the build itself, the ABS average build for a new NSW house was 2.99 quarters in 2025-26. If you're near Five Dock town centre and wondering about two homes instead of one, our Five Dock new homes page covers the Low and Mid-Rise rules.
Before the house comes down in Five Dock
Six things to have settled before anyone books a machine.
- 01
Approval for the new home that includes demolition
- 02
Heritage status on the planning certificate
- 03
A hazardous materials survey of the existing house
- 04
Licensed asbestos removal booked and cleared
- 05
Services disconnected or capped
- 06
Dilapidation reports on the neighbouring houses
House demolition in Five Dock
Can I demolish now and design the new house later?
You can seek approval for demolition on its own, but you'd then hold an empty block while the new home is designed and approved. Approving both together is usually the better plan.
Do I need separate approval to demolish?
Usually not. Demolition is normally approved in the same complying development certificate or development application as the new home. Check that the approval covers both before work starts.
Who removes the asbestos?
A licensed asbestos removalist, after a survey identifies it. We arrange the survey, the removal and the clearance as part of the rebuild.
Do you do demolition only?
We take on demolition as part of a knockdown rebuild, so the approval, the demolition and the new home run under one plan and one contract.
What does a new single-storey home cost after demolition?
Our benchmark for a single-storey new home from Rawlinsons' Sydney rates is $565k–$980k + GST, build only. Demolition and site costs are priced once the survey and inspections are done.
Sources and references
Costs are from the Rawlinsons handbook with the local cost index applied; rules and timeframes are checked against the sources below.
- City of Canada Bay
- Rawlinsons Australian Construction Handbook, Rawlhouse Publishing
- Environmental Planning and Assessment Act 1979 (NSW)
- State Environmental Planning Policy (Exempt and Complying Development Codes) 2008
- Asbestos, SafeWork NSW
- Building and renovating, Sydney Water
- Building or renovating a home, NSW Government
- Search heritage databases, NSW Environment and Heritage
- NSW Planning Portal Spatial Viewer (zoning, FSR and hazard maps)
Clear the block in the right order