
Campbelltown 2560 · Campbelltown City Council
Home Extensions Campbelltown
A good extension in Campbelltown starts below ground, with the soil and the slab.
Most owners picture the finished family room. The decisions that make it work come earlier: what the ground will carry, how the new slab meets the old house, where the stormwater goes and which approval the design can pass. This page goes through them in the order they come up.
Short answer
What does a ground floor extension in Campbelltown involve?
The work starts below ground. A geotechnical report classifies the soil, an engineer designs the footings for it, and the new slab is set to the existing floor level. If the design meets the Housing Code, a certifier can approve it as a complying development certificate. If not, it's a development application to Campbelltown City Council.
Written and reviewed by Oliver Alameri
Licensed builder, NSW Contractor Licence 487805C · Founder, Buildana
Fact-checked
Joining a new slab to an existing house
A ground floor addition sits on its own footings, beside footings that have been there for years. The engineer needs to know what the soil is before designing them, so a geotechnical report comes first. It classifies the site, and the slab and footing design follow from that class.
Then the levels. The new floor should meet the existing floor without a step, unless you want one. A survey of the existing floor and ground levels sets that up, and it also shows how much cut or fill the new slab needs.
Where new meets old, the engineer details the junction so the two parts can move slightly without cracking the finishes. The new roof needs its own downpipes and a lawful place for the stormwater to go, and existing downpipes in the way get moved.
- Geotechnical report on the soil
- Survey of existing floor and ground levels
- Engineer's footing and junction details
- Stormwater from the new roof
The family room is the easy part. The slab under it is where extensions go right or wrong.
Pipes under the back yard
The back yard is where most ground floor additions go, and it may also be where the sewer runs. Sydney Water has rules for building over or next to its pipes, so find out where they are before the plan is drawn, not when the excavator finds them.
Your own drainage matters too. A new bathroom or laundry in the addition needs a fall to the sewer, and that can decide where those rooms can sit.
Planning an extension in Campbelltown?
Send the address and a photo of the back of the house. Oliver will respond within 4 working hours for a free initial conversation about what the block and the slab allow.
0476 300 300What the published rates say
Rawlinsons gives $2,360–$2,550/m² for a framed and clad ground floor addition of 75–125m², and $2,630–$2,840/m² in brick veneer. A full first floor addition is $3,930–$4,230/m² for 75–100m². All are Sydney rates, excluding GST, escalated to the ABS September 2026 index.
A bathroom fitted out in an addition adds $36,850–$41,800 and a kitchen $30,800–$34,650, both including GST, on Rawlinsons' figures. The rate times the floor area gives you a first figure. The soil, the levels and the drainage above are what move it once we've seen the site.

Getting it approved in Campbelltown
The Housing Code covers alterations and additions as well as new homes, on lots in the R1, R2, R3, R4 and RU5 zones of at least 200m² and 6m wide. If the design meets every standard, a certifier can approve it, and a CDC must be decided within 20 days where neighbours are notified (10 days otherwise).
If it doesn't, the application goes to Campbelltown City Council as a DA, where a DA has a 40-day assessment period. Start with the section 10.7 planning certificate. It shows the zoning and whether the lot is bush fire prone or flood affected, either of which can change the approval path.
Thinking of building it yourself?
In NSW an owner-builder needs a permit for work valued over $10,000 and has to complete an approved course for work over $20,000 in value. You take on the builder's responsibilities: trades, inspections, insurance and defects.
If you use a builder, work valued at $20,000 or more including GST needs home building compensation cover before the builder takes money or starts. You can check the certificate on Service NSW's HBC Check, and the builder's licence on Verify NSW.
What I check first on a Campbelltown extension
These decide the design and the price before the floor plan does.
- 01
Zoning, bush fire and flood status on the planning certificate
- 02
A geotechnical report for the footing design
- 03
Existing floor levels and how the new slab will meet them
- 04
Where the sewer and stormwater pipes run
- 05
Where new wet areas can drain
- 06
Whether the design can meet the Housing Code for a CDC
Campbelltown extension questions
Do I need council approval for an extension in Campbelltown?
You need an approval, but not always from council. If the design meets the Housing Code, a certifier can issue a complying development certificate. If it doesn't, it's a development application to Campbelltown City Council.
Can I live in the house during a ground floor extension?
Usually, for most of it. The addition is built beside the house, and the disruption comes when the opening into the existing house is cut and the services are connected. Your builder should set those stages out in the programme.
Is an extension cheaper than knocking down and rebuilding?
For a single room or two, usually. For a large addition plus a renovation of the existing house, compare both. A knockdown rebuild starts with a new slab for the whole house rather than joining new to old.
Do you take on other building work in Campbelltown?
Yes. We design and build new homes, duplexes, renovations and extensions across Sydney from our studio in Fairfield. Send the address and Oliver will tell you plainly whether it's a job we can take on.
Sources and references
Costs are from the Rawlinsons handbook with the local cost index applied; rules and timeframes are checked against the sources below.
- Campbelltown City Council
- Rawlinsons Australian Construction Handbook, Rawlhouse Publishing
- Environmental Planning and Assessment Act 1979 (NSW)
- State Environmental Planning Policy (Exempt and Complying Development Codes) 2008
- Building on bush fire prone land, NSW RFS
- Home Building Act 1989 (NSW)
- Building and renovating, Sydney Water
- NSW Planning Portal Spatial Viewer (zoning, FSR and hazard maps)
- Environmental Planning and Assessment Regulation 2021 (NSW)
- Licence check, Verify NSW (Service NSW)
Start with the ground under it
Send the address and what you want the extension to do. Oliver will respond within 4 working hours for a free initial conversation, not a sales pitch.